DAY:
|
DATE:
|
OPERATION:
|
|
29.
|
11/23
|
6062'
TD, Drilled into Granite, Bottom 700' of formations were gone, will
make a decision by 9:00 a.m. Currently logging, does not look favorable |
|
28.
|
11/22
|
Depth 6020'
Drilling 6-7 minutes per foot, drilling shales, silt stones and
dolomite, should TD sometime late Friday or early Saturday.
Happy Thanksgiving!
|
|
27.
|
11/21
|
Depth
5888' Drilling 6-7 minutes per foot, presently tripping for bit |
|
26.
|
11/20
|
Depth 5676'
Drilling 4-5 minutes per foot
Potasi Dolomite
- slight show of gas, drilling ahead 5-7 minutes per foot
|
|
25.
|
11/19
|
Depth
5435' Drilling 5-7 minutes per foot, tripped for bit last 24 hours |
|
24.
|
11/18
|
Depth
5309' Drilling 8-9 minutes per foot, slight show of gas in the Oneida,
presently drillling into the top of the Cambrian. |
|
23.
|
11/17
|
Depth
5062' Drilling 4-5 minutes per foot, no show
|
|
22.
|
11/16
|
8:00 a.m. Depth 4940' - no shows Drilling 5 minutes per ft. |
|
21.
|
11/15
|
Depth 4630' Drilling 4-5 minutes per foot
10:00 a.m. Depth 4660' - slight show of oil in Knox not good enough
to test |
|
20.
|
11/14
|
We expect the
St. Peter @ 4100+ late this morning
Depth 4475 drilling
4-5 minutes per foot Drilled throught St. Peter, no show, into top
of Knox at 4300' presently at 4500', getting ready to trip for bit
|
|
19.
|
11/13
|
Depth 3820'
Drilling 3 minutes per foot 4100' should be St. Peter later today
Depth 4020'
Drilling 3-4 minutes per foot Trip for bit
|
|
18.
|
11/12
|
Depth 3796' Drilling 3 minutes per foot Barlow 1089' +12 St. Gen 1389'
+22 Borden 2044' + 80' Trenton 3410 + 100' Show of gas in the Trenton
Black River 3518' + 100' |
|
17.
|
11/11
|
Depth 3333' Drilling 2 minutes per foot |
|
16.
|
11/10
|
Depth 2920' Drilling 3-4 minutes per foot |
|
15.
|
11/9
|
Depth 2597' Drilling 3-4 minutes per foot, Trip for bit |
|
14.
|
11/8
|
Depth 2334' Drilling 3-4 minutes per foot |
|
13.
|
11/7
|
Depth
1943' Drilling 2-3 minutes per foot, Trip for Bit |
|
12.
|
11/6
|
Depth
1616', trip for bit, drilling 3-4 minutes per foot |
|
11.
|
11/5
|
Depth 1304' Set 1304' of 8 5/8" casing ready to start drilling |
|
10.
|
11/4
|
Depth 1304' Ready to run 8 5/8" casing |
|
9.
|
11/3
|
Depth 1188' Drilling 5-7 minutes per foot |
|
8.
|
11/2
|
1068' drilling 6-8 minutes per foot |
|
7.
|
11/1
|
1161' @ 4 minutes per foot Hole deviated 6.25 degrees Shut down, plug
back with cement to 1000' at 8:00 a.m. Waiting on cement to set to
start drilling again. |
|
6.
|
10/31
|
Drilling at 973' at 4 minutes per foot. |
|
5.
|
10/30
|
Surface
pipe came loose. Had to reset surface pipe. Back to drilling @ 700'
at 5:45 a.m. |
|
4.
|
10/29
|
Depth 505'; Drilling 1 minute per foot 12 1/4" hole. |
|
3.
|
10/28
|
Depth
48'; start drilling 17 1/2" hole @ 7:00 p.m. Set 48' of 13 3/8" casing,
cement with 60 sacks 3" calcium Ca Cl2 with plug down & 12:15 a.m.
presenlty nipple up & will start drilling 12 1/4" hole. |
|
2.
|
10/27
|
Finish
rigging up, set steel pits and start drilling 17 1/2" hole. |
|
1.
|
10/26
|
Will
finish moving rig to location and rig up. |
|
.
|
10/25
|
Continue
moving equipment, did not start rigging up due to heavy rain and storms.
Will rig up tomorrow. |
|
.
|
10/24
|
Continue
moving rig 14 to location and start rig up. |
| . |
10/23
|
Start
moving Rig 14 to location and begin building location. |