Howard Energy Corporation
P.O. Box 693
Mt. Carmel, Illinois
618-263-8110



WELL DATA

Flanagan #10D-1
~ Permit #(059900)
Elevation: (GL 445')
Section 10, TWP: 3S - RGE: 2E
(360'N & 330'W SEc SE NE)
Jefferson County, Illinois

EST FORMATION TOPS~(Cory Cantrell)
Lower Kincaid Ls (1615'), Massive Menard Ls (1860'), Little Menard Ls (1920'), Vienna Ls (1950'), Tar Springs Ss (1980'), Glen Dean Ls (2433'), Golconda Lm & Sh (2160'), Barlow Ls (2290'), Upper Renault (2500'), Lower Renault (2530'), Aux Vases (2550'), St Gen (2627'), St Louis (2715'), Salem (3040'), Warsaw (3360'), Chouteau Ls (4120'), Trenton (5400')

 

MORNING REPORT SUMMARY


Historical Data

September, 2009

DAY:
DATE:
                                        OPERATION:
19
9/27
Dwn on loc, RDMO loc tomorrow. Past 24hrs finish LDDP/collars, plug:(2650'-2400' w/85sx, 845'-635' w/75sx, 270'-0' w/125sx, rat hole~mouse hole w/25sx) total 310sx. Finish plugging @(11:00AM 9/26/09). Npl dwn BOP~prepare to move.

END OF REPORT
18
9/26
Preparing to plug, past 24hrs finish logging @(4:45PM 9/25/09), Ran DST #2~Trenton.TOH w/DST, LDDP (1/2 of string) finish pulling test tool, retrieve results. Finish lay dwn collars~ TIH w/plug pipe.
17
9/25
Depth 5802', TD @(6:45PM 9/24/09), Logging at present! Was drlg(4-6min/ft), 24hr footage(158'). HOB #6(69:26). Vis 83, mud wt 9.4, wtr loss 7.2, pH 10.5. Est mud cost $23,010. At TD short trip, cond hole, TOH, start logging @(4:00AM)~est time of log completion(10:30AM).
16
9/24

Depth 5644', drlg(4-6 min/ft), 24hr footage(257'). HOB #6(58:11). Vis 67, mud wt 9.2, wtr loss 7.2, pH 10. Est mud cost $20,472. Re-evaluated Trenton Top~5630'+/- Est TD @ 5780' to log!!

ADDITONAL INFORMATION FROM CRAIG @ 9:20 A.M. - CRAIG SAID WE HAVE A NICE BREAK AND A GOOD SHOW OF OIL IN THE TRENTON AT ABOUT 5650'

15
9/23
Depth 5387', drlg(5-6min/ft), 24hr footage(213'). HOB #6(35:39). Vis 60, mud wt 9.2, wtr loss 7.2, pH 10. Est mud cost $19,172. Drlg in Trenton (Top @5380' +/-) show of oil was noted in top 10' of zone~fractures. We are currently drilling the Trenton at 7:30 a.m. this morning.
14
9/22
Depth 5174', drlg(5-7min/ft), 24hr footage(156'). HOB #6(14:28). Vis 62, mud wt 9.2, wtr loss 7.2, pH 9.5. Est mud cost $16,143. Past 24hr TOH~bit chng!!
13
9/21
Depth 5018', drlg(6-12min/ft), 24hr footage(167'). HOB #5(46:40). Vis 65, mud wt 9.1, wtr loss 7.2, pH 10. Est mud cost $14,878. Prepare to TOH~chng bits !!
12
9/20
Depth 4851', drlg(7-9min/ft), 24hr footage(70'). HOB #5(26:41). Vis 65, mud wt 9.1, wtr loss 8, pH 9. Est mud cost $14,199. Past 24hrs TOH ck bit~TIH w/PDC bit, made 1' TOH~TIH w/Tri cone bit & resume drlg.
11
9/19
Depth 4781', drlg(4-6min/ft), 24hr footage(165'). HOB #5(17:56). Vis 63, mud wt 9.2, wtr loss 8, pH 9. Est mud cost $11,771. Past 24hrs TIH w/bit chng pick up new collars !
10
9/18
Depth 4616', Out of hole chng bits~pick up drill collars then TIH w/tri cone bit. Was drlg(12-30min/ft), 24hr footage(21'). HOB #4~PDC(4:03). Vis 64, mud wt 9.2, wtr loss 8, pH 9. Est mud cost $10,000. Past 24hrs TOH~bit chng, work on pmp clutch, TIH w/ PDC bit~would not drill, TOH to chng bits.
9
9/17
Depth 4595', TOH~ck bit Was drlg(6-10min/ft), 24hr footage(496'). HOB #3~PDC(61:03) Vis 60, mud wt 9.1, wtr loss 8, pH 9. Est mud cost $9957. Shows of oil noted in Lingle & Geneva Dolom.
8
9/16
Depth 4099', building volume in pits~were losing fluid!! Was drlg(1min/ft), 24hr footage(565'). HOB #3~PDC(42:04). Vis 57, mud wt 9.2, wtr loss 7.2, pH 10. Est mud cost $7020
7
9/15
Depth 3534', drlg(1-2min/ft), 24hr footage(602'). HOB #3~PDC(28:10). Vis 56, mud wt 9.2 wtr loss 8.8, pH 9. Est mud cost $5152.
6
9/14
Depth 2932', drlg(2-3min/ft), 24hr footage(370'). HOB #3~(9:09). Dev surv(3/4 @2775'). Vis 70, mud wt 9.1. Est mud cost $4,094. Past 24hrs Ran DST #1, recover results,TIH~resume drlg operations.
5
9/13
Depth 2562', cond hole for DST #1~Aux Vases. Was drlg(1-2min/ft), 24hr footage(817') HOB #2~PDC(31:29). Dev surv(3/4 @1765', 1 @2018', 3/4 @2371', 1 @2522'). Vis 57,mud wt 8.9. Est mud cost $2087. At stop depth~short trip & cond hole for test.
4
9/12
Depth 1745', drlg(2-3min/5'), 24hr footage(1480'). HOB #2~PDC(15:05). Dev surv(1 @505', 0 @1010', 1/2 @1545'). Drlg w/frsh wtr. Past 24hrs WOC, drill cmt, resume drlg 7 7/8" hole.
3
9/11
Depth 265', WOC & TIH~to drill cmt. Past 24hrs finish RURT, drill 12 1/4"surf hole, run (255' of 8 5/8"csg set @265')cmt w/180sx 3%CaCl-2. PD @(9:00PM 9/10/09). WOC, NU~BOP & tst to 300#. Depth 265', WOC & TIH~to drill cmt. Past 24hrs finish RURT, drill 12 1/4"surf hole, run (255' of 8 5/8"csg set @265')cmt w/180sx 3%CaCl-2. PD @(9:00PM 9/10/09). WOC, NU~BOP & tst to 300#.
2
9/10
Finish RURT, will start drlg operations~12 1/4"surface hole.
1
9/09
Moving Geo. N. Mitchell Drlg Co Rig #9 to loc. Will RURT tomorrow and commence drlg operations
.
9/08
Finish Bldg loc & prepare to move equipment in.